Pre-Purchase & Structural Quality Audit

Plot 412, Sector J, Phase 6, DHA, Lahore
Score Board
Grade B (Good Quality - Minor Snags)
Overall Score:
86/100
Earned: 9.5 / 11 Points (Pass = 1.0, Attn = 0.5, Fail = 0.0)
Critical Issues:
0
Attention Items:
3
Pass Rate:
73%
Executive Summary
Engineering Audit Summary

Comprehensive Pre-Purchase & Engineering Quality Audit conducted at DHA Phase 6, Lahore. Structural frame and concrete columns show sound load-bearing continuity with proper concrete compaction.

Two attention items were documented: capillary moisture dampness on the southern retaining wall cold joint requiring PU chemical injection, and localized honeycombing on Beam B-3 junction requiring non-shrink polymer repair mortar.

Evidence
Evidence Evidence
Priority Action List
Action Required
Low 1. High Priority: Inject hydrophilic polyurethane grout into basement cold joint.
Medium 2. Medium Priority: Chip aggregate and patch Beam B-3 with Sika MonoTop non-shrink mortar.
Low 3. Low Priority: Maintain 14-day continuous wet curing.
Expert Recommendations
Civil Engineering Advice

Overall structural integrity is sound. Property is structurally approved subject to minor snag rectification prior to interior plaster and finishes.

Audit conducted according to Building Code of Pakistan (BCP) & ASTM Standards.
Lead Inspector
Verified Independent Inspector
EM
Engr. M. Nadeem
Lead Structural & Quality Assurance Auditor (PEC Reg. #PEC/CIVIL/38491)
5.0 / 5.0 • 280+ Audits Completed PEC Registered
Inspected Property: Plot 412, Sector J, Phase 6, DHA, Lahore 1 Kanal (approx. 5,400 sq ft) • Scheduled: 12 Oct 2026 (Morning (10:00 AM - 01:00 PM))
Completed Ref: INS-2026-LHR-09412

Report Sections

Detailed engineering checkpoint breakdown & on-site verification

Plinth protection & DPC damp-proof course integrity Continuous bituminous DPC layer verified without bridging.
Pass Evidence
No visible foundation settlement or differential cracks Zero differential subsidence detected along boundary retaining lines.
Pass

Column plumb alignment & cross-sectional geometry All vertical columns within +/- 3mm tolerance.
Pass Evidence
Beam-column joints honeycomb & segregation check Minor cosmetic surface voids on first-floor porch lintel. Requires polymer mortar touch-up.
Attention Evidence

Brickwork bond pattern & mortar joint thickness Proper 1:4 cement mortar with consistent 10mm joints.
Pass
Plaster hollow sounding & shrinkage cracks Parapet wall hairline shrinkage crack observed. Non-structural; requires elastomeric filler.
Attention Evidence

Concealed PPRC pipe pressure integrity & joint welds Pressure tested at 8 bar for 2 hours with zero gauge pressure drop.
Pass Evidence
Pipe sleeve sealing in wet-area risers Powder room pipe sleeve not filled with non-shrink sealant. Potential capillary moisture bridge.
Attention

Distribution Board circuit breakers & wire gauge sizing Standard Pakistan Cables copper wiring with Hager MCBs installed.
Pass Evidence
Earth-pit ground electrode resistance test Earthing electrode impedance reading 3.2 Ohms (well below 5.0 Ohm threshold).
Pass

Thermal imaging moisture scan of bathrooms & roof Infrared thermal scan confirmed dry screed and fully functional bitumen waterproofing membrane.
Pass Evidence
Rate Inspector Performance